Design and Build of New Waste Water Treatment Plant, 13km pipeline work and outfall pipeline incorporating, SBR cells/stormtank, inlet works building, administration building, sludge treatment building, sludge acceptance building & sludge mixing tanks, 1,500m of 900dia inlet pipe, 1,500m 1,050dia. outlet pipe, 600m outfall and 20 manholes.
This project is the civil element of a joint venture contract between Fleming Construction and Jones Environmental Ltd for the design, build and operation of the Wexford Main Drainage.
Contract Duration: Commenced February 2002
Completion Date: November 2003
|