Site Services – Civil works involving road construction, car parks, drainage, ducting, firemain installation, etc.
CB2 – New production building
Utilities Building – New Plant Room Building
MCC/Foam Building- Construct buildings, install services & finishes.
CB1 Extension - Building extension, services & fit-out.
Fire Retention Pond – Construction of a large concrete holding tank.
Canteen Extension – New building, including service’s installation and total fit-out.
Drum Storage Park Extension – Concrete Yard slab and associated drainage.
Old Laboratory Building Demolition
All of these works involved working within and around an existing live Pharmaceutical factory to stringent health & safety standards, incorporating tight programme restraints and dedicated plant shut down work activities. |